CalendarFUS News NewsletterLive ServiceSermonsPodcast/RSSSearchLeadership


First unitarian Society of Madison
Hard Hat Update

Pithy Construction News from "Beacon Street West” (FUS) for July 25 to August 1, 2007


Hi Everyone – Wednesday already, and time once again for a Hard hat update.  I can say this – there are lots of people running around in the A and B wings, doing lots of stuff! And now, here’s Dave to fill you in… See you! – Harry Carnes

Drilling holes in the foundation for new electrical lines.
A fire alarm system is being hard-wired into the remodeled sections of the building

 


Preservation Update
After examining  the samples from the paint probe, we have narrowed the selection to four. They may be viewed in the back rows of the Auditorium.  Feel free to share your opinions with the members of the Preservation Committee. There will not be a general vote.

The crews installing the ventilator will be working evenings next week to avoid the daytime heat in the attic.

Building
This week’s surprise was discovering that the ductwork that has to be lowered to lower the lower B Wing floor is embedded in 3 feet of concrete.  The laborers from Findorff are managing to stay upbeat as they jackhammer away. The new floor should be poured next week, and then the walls can be framed. New doors are ordered as is the new office furniture.

The “Shop” is starting to work on the laminated rafters for the new auditorium.

-  David Weber, Owners Representative

 

Making way for new electrical lines. Room B-16 is almost ready for sprinklers to be installed.

 

Drilling holes in the foundation for new electrical lines.The "Big Dig" at the bottom of the stairs.

 

 

Who We Are | Worship | Education | Opportunities | Meeting House | Social Justice | Music | Contact | Search